Adding battery storage to a charging site is first a grid-connection and energy-management decision, and only then a software one. A battery pays off only if the system that controls the chargers can also control the battery, within the limits of the site connection. European regulation makes this easier, but it does not require it.
What a battery does on a charging site
A stationary battery can cover part of the site demand during peaks, so the site draws less power from the grid at those moments. In practice this can lower the connection capacity you ask the network operator for, and reduce peak-related charges where your tariff includes them. It can also store local solar production for later use, and, depending on the market, be offered as flexibility.
How much you gain depends on your connection offer, your tariff and your charging profile. We do not publish a general figure: model each site with your own data.
What the regulation says, and what it does not
Protocols: do not mix up three different links
A site with storage involves three separate communication links.
1. Charger to CSMS. This is OCPP. OCPP 1.6 and 2.0.1 are not compatible with each other. OCPP 2.1 extends 2.0.1 and adds functional blocks for distributed energy resources and bidirectional flows, which 2.0.1 does not have (Open Charge Alliance).
2. Vehicle to charger. This is ISO 15118. ISO 15118-2 does not cover advanced smart charging or bidirectional charging; ISO 15118-20 does. Under the delegated regulation, public points installed or renovated from 1 January 2027 must support at least ISO 15118-20 (Delegated Regulation 2025/656).
3. Battery system to site controller. This link does not belong to OCPP or ISO 15118. Battery and inverter vendors expose their own interfaces, so ask which interface is available and who runs the control loop.
AFIR does not name OCPP. Using it remains a practical way to keep several brands of chargers under one supervision tool.
Checks before you commit
What to do this week
List your sites where the connection capacity limits the number of chargers. For two of them, request a connection offer and a tariff statement, and ask your equipment suppliers for the control interface of their storage product. GFO Omni is a CSMS that supervises charging points over OCPP 1.6, 2.0.1 and 2.1.