The Megawatt Charging System (MCS) is the connector and communication framework designed for electric trucks and other heavy vehicles. Its standards are now published, but its European rollout is not dated by any official source we could read. This article separates what is settled from what is not, so an operator can prepare sites without betting on a calendar.
Which MCS standards exist
Two documents define the system today.
CharIN announced the IEC publication on 9 February 2026 and describes MCS standardisation as complete. A later CharIN headline mentions IEC 61851-23-3:2026 as completing the framework; we did not read the article, so check the text before relying on it.
A figure to handle with care
The often-quoted 3,75 MW is a calculation, not a figure written in a standard. CharIN's MCS page gives 1 250 V and 3 000 A and describes the requirements as still under discussion. The IEC specification allows up to 1 500 V. Only the current, up to 3 000 A, is common to both. When you quote a power level to a customer, say which voltage you assume.
What AFIR sets for heavy-duty charging
AFIR, Regulation (EU) 2023/1804, has applied since 13 April 2024. Article 4 sets heavy-duty targets by pool, in kW, on the TEN-T network. They are targets that Member States must ensure, not an obligation on each operator.
These figures concern heavy vehicles and are not specific to MCS. The regulation also notes that standards for heavy-duty vehicles were still being developed when it was adopted.
What this means for a CPO
Megawatt-class sites are first a grid question. A 3 600 kW pool does not fit on a connection sized for cars. The Directive 2019/944 asks Member States to facilitate the connection of charging points, but no official figure we found gives connection lead times for charging in Europe. Treat the DSO request as the critical path.
Truck sites also depend on how the vehicle is used. Safe parking areas and depots have long dwell times, where several lower-power points under managed charging can serve a fleet at a lower connection capacity than one megawatt-class point. The choice between the two depends on the fleet schedule, not on the standard.
Finally, do not assume protocol support. We found no verified statement on how OCPP versions handle MCS sessions. Ask each hardware supplier which OCPP version their megawatt product speaks and which messages it supports, in writing.
This week
List the heavy-vehicle routes near your sites and compare them with the TEN-T network. Ask your DSO what connection capacity is available. Ask hardware suppliers which MCS standard version their product follows. GFO Omni is a CSMS supporting OCPP 1.6, 2.0.1 and 2.1 that supervises charge points.